The Peka Peka to Ōtaki Expressway, taken by drone on November 14, 2022. The new road opens this week.
The Peka Peka to Ōtaki Expressway now has an official opening ceremony date – albeit one two years late, $230 million over budget, and just days before Christmas.
Waka Kotahi NZTA has sent out invitations to the Wednesday morning opening ceremony of the $445m, 13 kilometre, four-lane stretch of State Highway 1 north of Wellington. Waka Kotahi cannot say when the road will be open to the public. However, it is expected before Christmas.
Work began on the new road – which connects to the 18km Mackays to Peka Peka expressway – in 2017.
It was scheduled to open in 2020 but, like the Transmission Gully motorway, (which connects to Mackays) it was pushed back. The delay was blamed on Covid-19 issues and changes to the project design.
READ MORE:
* Transmission Gully: The Christmas present commuters are eager to open
* Deadly road can’t wait until end of decade to be replaced, AA says
* Ōtaki expressway cost shoots up to $405 million as project scope and paving costs increase
Also like Transmission Gully, which was originally budgeted to cost $850m but ended up coming in at $1.35 billion, the expressway has blown out in costs.
STUFF
Conservationists feared ferrets were using the MacKays to Peka Peka Expressway to travel south (Video first published in 2019)
The road was budgeted to cost $215m in 2009 but that rose to $330m by the time construction began, $405m by 2020, and now sits at $445m.
The expressway linking Transmission Gully to the Peka Peka to Ōtaki Expressway, started at an estimated $550m in 2009, but was finally completed for about $630m.
Waka Kotahi regional infrastructure delivery manager Jetesh Bhula in late November said the Peka Peka to Ōtaki project team was hoping for favourable weather to open the road before Christmas.
The project included the construction of 10 bridges, including the 330m long Ōtaki River Bridge, a 1.3km realignment of the North Island Main Trunk railway line, and building almost 9km of local roads.
Work will begin on the Ōtaki to North of Levin Expressway, which will join onto the northern end of the Peka Peka to Otaki Expressway, in 2025 for an opening date of approximately 2029.