With the Horowhenua District Council yet to decide on the future of the Levin Landfill, ways of mitigating the site’s effects on the environment are being investigated.
The landfill, a 72-hectare site between Levin and Hokio Beach, houses the old unlined dump, which opened in the 1970s and closed in 2004, and the new lined landfill. The landfill stopped taking waste in 2021 while a decision on its future is made.
The council’s consultation period for the landfill’s future ends on Monday, then submissions will be presented to the council. A decision has to be made this financial year.
There are three options: to close the landfill permanently and maintain the site; close the landfill but have alternative uses for the site including dumping materials such as rocks and soil to earn some income; or reopen the landfill. The preferred option for councillors is closure but with alternative use.
READ MORE:
* Horowhenua councillors vote for closure of ‘contentious’ Levin Landfill
* Levin landfill largely compliant with consents
* Levin landfill problems continue to get up people’s noses
The landfill has a consent to operate until 2037. While it is closed, Horowhenua’s waste goes to Bonny Glen Landfill near Marton.
The Horowhenua council says no leachate from the new landfill is going into the waterways, but it is working with a team to understand what is happening with the old dump. A report is due out in May.
Options for collecting leachate will be investigated.
The Horizons Regional Council rated the landfill as moderately non compliant for the 2020-21 assessment period.
Warwick Smith/Stuff
The new landfill, left, has a temporary cover while a decision on its future is made, and a permanent cover is being put on the old dump, right.
The council’s solid waste environmental adviser David McMillan said they had been given a list of options and they were working on those, but they were still waiting on the report.
The council was monitoring the old dump and was looking at options for remediating some loadings that were higher than allowed.
“We’re investigating right now to find out how bad things will get or when things will get better.
“We’re trying to put a picture together to figure out the best strategy going forward to manage any adverse effects.”
Boreholes at the landfill monitor water in various aquifers.
Warwick Smith/Stuff
Horowhenua District Council solid waste environmental adviser David McMillan says the new landfill is not causing any environmental problems.
Testing is done on the unlined old dump, but McMillan said there was no chemical activity that went to nearby Hokio Stream that reached trigger limits.
He said it was typical of an unlined landfill and what was coming out of the site petered off over time.
The old dump probably followed best practice at the time, but things had changed, he said.
The council was in the process of putting a new cap on the old dump.
They were “beefing up” the cap to the new consent regulation of 700mm of clay, then topsoil and grass will be put on top.
Warwick Smith/Stuff
The flare burns off any gases that escape from the landfill.
This stops water getting into what is buried underneath.
The new landfill has a temporary cap, but if a decision is made to close it, a permanent 700mm clay cap will be put on.
If the decision was made to reopen the facility, a new cell next to the existing landfill would have to be dug out and a new liner put in, which the council had originally planned to do anyway.
McMillan said the new landfill was lined and compliant, and was not causing any environmental problems.
The gas flare burns off any gases produced. About 10-50 cubic metres of waste water from the new landfill is piped to the wastewater treatment plant each day.
Warwick Smith/Stuff
A permanent clay cap is being put on the old dump.
About 514,000 tonnes of waste are in the new landfill, but McMillan estimated about 50,000 tonnes was in the old dump.
The council holds $6.2m of debt against the landfill due to capital development costs, including capping the old cells, building the flare and pumps.
The council was looking at ways of minimising waste in the region. McMillan said 32% of the region’s municipal waste was kitchen and green waste, so if that could be decreased it could save money.
The council is also investigating building a wetland at the site to help mitigate the environmental effects of anything seeping out of the old landfill.
Warwick Smith/Stuff
The landfill has been closed since 2021 while a decision on its future is made.



















Discussion about this post