Cost Update for Macquarie Point Stadium Revealed
The ongoing discussions surrounding the Macquarie Point stadium have become increasingly familiar, with a common refrain emerging: the devil is in the details.
Premier Jeremy Rockliff announced this morning via Facebook that the updated budget for the stadium has escalated from $1.13 billion to $1.23 billion. This news was met with a blend of relief and surprise from various stakeholders, many of whom had anticipated a more significant increase.
Broader Precinct Works Required
However, the complexities of the situation become evident when considering the essential infrastructure required for the stadium’s functionality. The broader precinct works at Macquarie Point, which are critical for the stadium’s operation, have not been included in the initial cost estimates.
Necessary upgrades for energy, water, and landscaping have necessitated an additional allocation of $132 million from the government. While these improvements will benefit not only the stadium but also future developments in the area, such as hotels and restaurants, they are vital for the stadium’s basic operations.
As a result, the total price now rises to $1.36 billion when including these infrastructural needs.
Project Costs Continue to Escalate
In addition to the aforementioned costs, there are expenses associated with facilitating the extra work and costs already incurred by the Macquarie Point Development Corporation (MPDC), which amount to $183 million. This brings the total estimated cost for the stadium and associated precinct works to $1.54 billion.
This figure is contingent on the project proceeding as planned throughout its development cycle.
Contingency Costs and Future Projections
Notably absent from the latest update is the contingency cost, which has traditionally been included in previous estimates. The government and MPDC have chosen to keep this figure undisclosed until the construction contract with BESIX Watpac is finalized. Previously, this amount was estimated at $174 million, representing approximately 14% of the earlier budget of $1.13 billion.
Applying the same contingency percentage to the new total brings the overall budget to an estimated $1.76 billion. The exact contingency amount will depend on the contract terms agreed upon with BESIX Watpac.
Rationale Behind Cost Increases
During a recent public accounts committee hearing, department secretary Kathrine Morgan-Wicks emphasized the importance of understanding the relationship between MPDC and the lead contractor. The costs may increase if more risks are transferred to the contractor or decrease if the state assumes more of the risks.
“For example, the contract cost will be higher as risks are transferred to the contractor, or lower if the state accepts risks.”
Additionally, the MPDC has indicated that external factors, such as the ongoing conflict in Iran and Australia’s competitive infrastructure landscape, have contributed to the rising costs. In an effort to manage expenses, the MPDC reported that they have “value managed” the project, achieving savings of $100 million primarily through design and delivery processes.
Breakdown of Current Costs
The current total of $1.54 billion encompasses various aspects of the project:
- The core construction of the stadium, including seating, roofing, and fit-outs.
- Infrastructure enhancements, such as stormwater and power upgrades, landscaping, and a car park that, while not essential for the stadium, will support broader precinct development.
- Project delivery costs covering consultancy fees, staffing, equipment, and insurance.
It is important to note that the estimated costs do not include the Northern Access Road, which is projected to cost $78.9 million and will be funded separately by Building Tasmania.
Financial Implications for Taxpayers
The updated budget does not factor in interest on additional borrowings necessary to cover these increased costs. As a result, the Tasmanian taxpayer will shoulder the burden of $1.29 billion through capital and borrowings, effectively nullifying the previously agreed state funding cap of $875 million.
However, Premier Rockliff has indicated that discussions are underway with the federal government, AFL, cricket, and private sector stakeholders regarding potential additional funding contributions.
Next Steps for the Project
The revised budget is set to be presented to the cabinet by November 30 and is anticipated to receive approval, with a construction contract expected to be signed shortly thereafter.
MPDC’s Anne Beach stated, “We’ve had our commercial and legal team, as well as our technical team, look at the detail submitted by [BESIX] Watpac. We’ve undertaken an analysis, and we’re confident that we can deliver within that budget.”